Temporarily close or divert a public right of way
On linear construction projects, rights of way will be recorded as part of the Land referencing exercise so that preparations can be made where diversion or closure is considered necessary by the project team.
FGP will prepare applications to temporarily close or divert a public right of way by means of a Traffic Regulation Order under Section 14 of the Road Traffic Act (1984). A definitive right of way may be closed for a maximum period of 6 months with no follow up order in the 12 months after. FGP will include the necessary mapping detail and grounds justifying the need. The aim is for a Traffic Regulation Order to be published following a successful application.
The grounds for such diversions need to be clear and unambiguous. Typically, the grounds will relate to construction being carried out on or near the right of way or, safety because of a likelihood of danger to the public in carrying out necessary works.
Occasionally, urgent short term closures by notice can be obtained for a maximum duration of 5 consecutive days.Â
Permanent diversions and closures
Permanent diversions and closures are inevitably more complex typically following a grant of planning permission or forming part of a Development Consent Order application. They are applied for under the Town and Country Planning Act 1990. Public rights of way may be closed or diverted for a variety of reasons and clear justification must be prepared because the consultation exercise is comprehensive.
The provision of an alternative route is vital to the application and needs to be agreed with landowners in the first instance. FGP will consider the situation with the project team and then the landowners and occupiers. Maps are prepared at each stage showing alternatives for consultation.
Once applied for, an Order will take 4 months to obtain if there is no objection. Both the Ramblers’ Association and the Open Spaces Society have a policy of objecting to Public Path Orders unless a clear public benefit can be shown. As a result, allowance needs to be made for additional time. It is important that applications include all necessary details so that further delays are not introduced when planning authorities ask for more detail.
Key Party Consultations
FGP will bring together key parties for consultation so that amendments can be made if necessary. As well as the Ramblers Association and Open Spaces Society, this will include Parish Councils and the British Horse Society where bridleways are involved.
In making the Order, the Council will have regard to the need for an alternative highway to be provided and the disadvantage or loss likely to arise because of the stopping up or diversion. Disadvantages will be weighed against the advantages of the development, which might include a community contribution.